August 6, 2018

Here’s what you can expect to see on site in the next two weeks:

This week, the construction crew will be forming and pouring the 10th floor and installing exterior block on the 2nd floor of the tower. They are also completing forming the first floor deck of the “C” section (the southern portion next to 1 Pierrepoint) and prepping to pour the 1st floor. We’ll continue to install the cocoon system to wrap the upper floors under construction, along with general housekeeping (cleanup and collection of trash and construction debris) and implementing site safety protocols. ConEdison will be working on Clinton Street.  No street closures are anticipated.

Next week (starting 8/13), the crew will be pouring the final concrete to form the mezzanine of the “C” portion. On the tower portion, they will form and pour the 11th floor and start forming the 12th floor.  They will also install exterior block on the 2nd and 3rd floors.  No street closures are anticipated.