August 20, 2018

Here’s what you can expect to see on site in the next two weeks:

This week, the construction crew will be forming and pouring the 11th floor, forming the 12th floor and installing exterior block on the 3rd floor of the tower. They are also prepping and pouring the first floor of the “C” section (the southern portion next to 1 Pierrepoint). We are also raising the hoist complex, as we move up the building.  General housekeeping (clean-up and trash collection) and implementation of site safety protocols will continue.  There are no planned street closures or off-site utility work.

Next week (starting 8/27), the crew will be pouring and forming the mezzanine of the “C” portion of the building. On the tower portion, they will pour the 12th floor and start forming and pouring the 13th floor.  They will also install exterior block on the 3rd and 4th floors, and exterior wall panels on the 2nd floor.  No street closures or off-site utility work are anticipated.