December 17, 2018

Happy Holidays! Here’s what you can expect to see on site in the next two weeks:

The week of 12/17, the construction crew will be pouring the 25th and 26th floors and installing block on the lower levels of the tower. Exterior wall waterproofing and stone panel installation is occurring up to the 3rd floor.  Mechanical and other interior work is ongoing up to the 18th floor. General housekeeping (clean-up and trash collection) and implementation of site safety protocols will continue.  ConEd is expected to be working on Clinton Street and there is a possible street closure. The DEP water connection is also in progress.

Next week (starting 12/24), the crew will pour the 27th floor. Exterior wall waterproofing and block installation at the exterior and lower levels will continue.  Stone panel installation will continue up to the 3rd floor. ConEd may still be working on Clinton Street and there is a possible street closure.