July 16, 2018

Here’s what you can expect to see on site in the next two weeks:

This week, the construction crew will be pouring the 7th floor deck in the tower portion of the site and erecting formwork for the 8th floor deck. They are also preparing to pour the foundation walls of the “C” section (the southern portion next to 1 Pierrepoint). The tower crane will be increasing in height. We’ll continue with general housekeeping (cleanup and collection of trash and construction debris) and implementing site safety protocols. There is no anticipated off-site utility work or street closures.

Next week (starting 7/23), the crew will be forming the first floor deck of the “C” portion. They will install the “Cocoon” system on the tower to wrap the upper floors under construction, as a safety measure.  No street closures are anticipated.