June 25, 2018

Here’s what you can expect to see on site in the next two weeks:

This week, the construction crew will be pouring the 6th floor deck in the tower portion of the site and erecting formwork for the 7th floor deck.  They are also preparing for a pour of the cellar deck in the “C” section (the southern portion next to 1 Pierrepoint) of the site. The installation of the hoist tower will be ongoing on the Cadman side. And behind the construction fence, the crew will be digging for the sewer connection on Clinton Street. We’ll continue with general housekeeping (cleanup and collection of trash and construction debris) and implementing site safety protocols. There is no anticipated off-site utility work or street closures.

Next week (starting 7/2), the crew will be pouring the cellar deck in the “C” portion. They will pour the 7th floor deck. No work is anticipated needing street closures. The site will be closed on July 4th. Happy Independence Day!