March 12, 2019

Here’s what you can expect to see on site in the next two weeks:

The week of 3/11, the construction crew will be pouring the 37th floor roof slab and delivering the rooftop mechanical equipment.  Block will be installed on floors 22-24 and exterior stone installation will continue on the Cadman Plaza West and Clinton Street elevations. Upturned beams will be poured on the 28th and 29th floors and windows will be installed on the 7th and 8th floors. Inside the building, interior framing will continue on the 5th and 6th floors. General housekeeping (clean-up and trash collection) and implementation of site safety protocols will continue.  ConEd is expected to be working on Clinton Street.

Next week (starting 3/18), the crew will pour the 38th floors. Block installation will continue on the 24th-26th floors. Exterior stone installation on Cadman Plaza West and Clinton Street will continue and windows will be installed up to the 8th and 9th floors. Upturned beams will be poured on the 30th and 31st floors. Interior wall framing will occur on the 6th-7th floors. ConEd is expected to be working on Clinton Street.