November 5, 2018

Here’s what you can expect to see on site in the next two weeks:

The week of 11/5, the construction crew will be forming and pouring the 21st and 22nd floors and installing block on the 12th and 13th floors of the tower. Upturned beams will be installed on the 14th and 15th floors.  Exterior wall waterproofing and exterior wall framing of the 1st will also occur on the tower portion.  The crew is installing 3rd floor block in the “C” section (the southern portion next to 1 Pierrepoint) on the west side. General housekeeping (clean-up and trash collection) and implementation of site safety protocols will continue.  ConEd is expected to be working on Clinton Street and there is a possible street closure.

Next week (starting 11/12), the crew will be installing block on the 3rd and 4th floors of the “C” portion of the building. On the tower portion, they will form and pour the 23rd floor and form the 24th floor.  They will also start limestone panel installation on the facade on Clinton Street.  Installation of exterior wall waterproofing, mechanical work for interior fit out from the 10th floor down, and exterior wall framing on the 1st floor Clinton St side will be ongoing. ConEd is expected to be working on Clinton Street and there is a possible street closure.