October 19, 2018

Here’s what you can expect to see on site in the next two weeks:

The week of 10/22, the construction crew will be forming and pouring the 18th and 19th floors and installing exterior block on the 11th and 12th floors of the tower. Upturned beams will be installed on the 12th and 13th floors.  Exterior wall waterproofing, exterior wall framing of the 1st floor and tube steel installation will also occur on the tower portion.  The crew is removing reshores and installing 2nd floor block in the “C” section (the southern portion next to 1 Pierrepoint). General housekeeping (clean-up and trash collection) and implementation of site safety protocols will continue.  ConEd is expected to be working on Clinton Street and there is a possible street closure by Con Ed or DDC on Clinton Street and Tillary.

Next week (starting 10/27), the crew will be pouring the 5th floor of the “C” portion of the building and installing block on the 3rd and 4th floors. On the tower portion, they will pour the 21st floor and form the 21st floor.  They will also install continue exterior wall waterproofing, mechanical work for interior fit out from the 10th floor down, and exterior wall framing on the 1st floor Clinton St side. DDC will continue work on Tillary and possibly the Sewer Connection for the project.  No street closures are anticipated.