Here’s what you can expect to see on site in the next two weeks:

The week of 9/24, the construction crew will be forming and pouring the 15th and 16th floors and installing exterior block on the 6th and 7th floors of the tower. Upturned beams will be installed on the 9th and 10th floors.  Exterior wall waterproofing and exterior wall framing of the 1st floor will also occur on the tower portion.  The crew is also prepping to pour the second floor of the “C” section (the southern portion next to 1 Pierrepoint). General housekeeping (clean-up and trash collection) and implementation of site safety protocols will continue.  ConEd is expected to be working on Clinton Street this week and there is a possible street closure by Con Ed or DDC on Clinton Street and Tillary.

Next week (starting 10/1), the crew will be forming the 4th floor of the “C” portion of the building and installing block on the 2nd floor. On the tower portion, they will pour the 17th floor and install block on the 7th and 8th floors.  They will also install upturned beams on the 10th and 11th floors and continue exterior wall waterproofing and framing.  The hoist complex will be installed on Clinton Street.  They will also install exterior block on the 3rd and 4th floors, and exterior wall panels on the 2nd floor.  DDC will continue work on Tillary and possibly the Sewer Connection for the project.  No street closures are anticipated.