November 5, 2018

Here’s what you can expect to see on site in the next two weeks:

The week of 11/5, the construction crew will be forming and pouring the 21st and 22nd floors and installing block on the 12th and 13th floors of the tower. Upturned beams will be installed on the 14th and 15th floors.  Exterior wall waterproofing and exterior wall framing of the 1st will also occur on the tower portion.  The crew is installing 3rd floor block in the “C” section (the southern portion next to 1 Pierrepoint) on the west side. General housekeeping (clean-up and trash collection) and implementation of site safety protocols will continue.  ConEd is expected to be working on Clinton Street and there is a possible street closure.

Next week (starting 11/12), the crew will be installing block on the 3rd and 4th floors of the “C” portion of the building. On the tower portion, they will form and pour the 23rd floor and form the 24th floor.  They will also start limestone panel installation on the facade on Clinton Street.  Installation of exterior wall waterproofing, mechanical work for interior fit out from the 10th floor down, and exterior wall framing on the 1st floor Clinton St side will be ongoing. ConEd is expected to be working on Clinton Street and there is a possible street closure.

October 19, 2018

Here’s what you can expect to see on site in the next two weeks:

The week of 10/22, the construction crew will be forming and pouring the 18th and 19th floors and installing exterior block on the 11th and 12th floors of the tower. Upturned beams will be installed on the 12th and 13th floors.  Exterior wall waterproofing, exterior wall framing of the 1st floor and tube steel installation will also occur on the tower portion.  The crew is removing reshores and installing 2nd floor block in the “C” section (the southern portion next to 1 Pierrepoint). General housekeeping (clean-up and trash collection) and implementation of site safety protocols will continue.  ConEd is expected to be working on Clinton Street and there is a possible street closure by Con Ed or DDC on Clinton Street and Tillary.

Next week (starting 10/27), the crew will be pouring the 5th floor of the “C” portion of the building and installing block on the 3rd and 4th floors. On the tower portion, they will pour the 21st floor and form the 21st floor.  They will also install continue exterior wall waterproofing, mechanical work for interior fit out from the 10th floor down, and exterior wall framing on the 1st floor Clinton St side. DDC will continue work on Tillary and possibly the Sewer Connection for the project.  No street closures are anticipated.

September 21, 2018

Here’s what you can expect to see on site in the next two weeks:

The week of 9/24, the construction crew will be forming and pouring the 15th and 16th floors and installing exterior block on the 6th and 7th floors of the tower. Upturned beams will be installed on the 9th and 10th floors.  Exterior wall waterproofing and exterior wall framing of the 1st floor will also occur on the tower portion.  The crew is also prepping to pour the second floor of the “C” section (the southern portion next to 1 Pierrepoint). General housekeeping (clean-up and trash collection) and implementation of site safety protocols will continue.  ConEd is expected to be working on Clinton Street this week and there is a possible street closure by Con Ed or DDC on Clinton Street and Tillary.

Next week (starting 10/1), the crew will be forming the 4th floor of the “C” portion of the building and installing block on the 2nd floor. On the tower portion, they will pour the 17th floor and install block on the 7th and 8th floors.  They will also install upturned beams on the 10th and 11th floors and continue exterior wall waterproofing and framing.  The hoist complex will be installed on Clinton Street.  They will also install exterior block on the 3rd and 4th floors, and exterior wall panels on the 2nd floor.  DDC will continue work on Tillary and possibly the Sewer Connection for the project.  No street closures are anticipated.

August 20, 2018

Here’s what you can expect to see on site in the next two weeks:

This week, the construction crew will be forming and pouring the 11th floor, forming the 12th floor and installing exterior block on the 3rd floor of the tower. They are also prepping and pouring the first floor of the “C” section (the southern portion next to 1 Pierrepoint). We are also raising the hoist complex, as we move up the building.  General housekeeping (clean-up and trash collection) and implementation of site safety protocols will continue.  There are no planned street closures or off-site utility work.

Next week (starting 8/27), the crew will be pouring and forming the mezzanine of the “C” portion of the building. On the tower portion, they will pour the 12th floor and start forming and pouring the 13th floor.  They will also install exterior block on the 3rd and 4th floors, and exterior wall panels on the 2nd floor.  No street closures or off-site utility work are anticipated.

August 6, 2018

Here’s what you can expect to see on site in the next two weeks:

This week, the construction crew will be forming and pouring the 10th floor and installing exterior block on the 2nd floor of the tower. They are also completing forming the first floor deck of the “C” section (the southern portion next to 1 Pierrepoint) and prepping to pour the 1st floor. We’ll continue to install the cocoon system to wrap the upper floors under construction, along with general housekeeping (cleanup and collection of trash and construction debris) and implementing site safety protocols. ConEdison will be working on Clinton Street.  No street closures are anticipated.

Next week (starting 8/13), the crew will be pouring the final concrete to form the mezzanine of the “C” portion. On the tower portion, they will form and pour the 11th floor and start forming the 12th floor.  They will also install exterior block on the 2nd and 3rd floors.  No street closures are anticipated.

July 23, 2018

Here’s what you can expect to see on site in the next two weeks:

This week, the construction crew will be pouring the 8th floor deck in the tower portion of the site and forming the 9th floor deck. They are also forming the first floor deck of the “C” section (the southern portion next to 1 Pierrepoint). We’ll continue with general housekeeping (cleanup and collection of trash and construction debris) and implementing site safety protocols. There is no anticipated off-site utility work or street closures.

Next week (starting 7/30), the crew will be pouring the first floor deck of the “C” portion. They will continue to install the “Cocoon” system on the tower to wrap the upper floors under construction, as a safety measure.  No street closures are anticipated.

July 16, 2018

Here’s what you can expect to see on site in the next two weeks:

This week, the construction crew will be pouring the 7th floor deck in the tower portion of the site and erecting formwork for the 8th floor deck. They are also preparing to pour the foundation walls of the “C” section (the southern portion next to 1 Pierrepoint). The tower crane will be increasing in height. We’ll continue with general housekeeping (cleanup and collection of trash and construction debris) and implementing site safety protocols. There is no anticipated off-site utility work or street closures.

Next week (starting 7/23), the crew will be forming the first floor deck of the “C” portion. They will install the “Cocoon” system on the tower to wrap the upper floors under construction, as a safety measure.  No street closures are anticipated.

June 25, 2018

Here’s what you can expect to see on site in the next two weeks:

This week, the construction crew will be pouring the 6th floor deck in the tower portion of the site and erecting formwork for the 7th floor deck.  They are also preparing for a pour of the cellar deck in the “C” section (the southern portion next to 1 Pierrepoint) of the site. The installation of the hoist tower will be ongoing on the Cadman side. And behind the construction fence, the crew will be digging for the sewer connection on Clinton Street. We’ll continue with general housekeeping (cleanup and collection of trash and construction debris) and implementing site safety protocols. There is no anticipated off-site utility work or street closures.

Next week (starting 7/2), the crew will be pouring the cellar deck in the “C” portion. They will pour the 7th floor deck. No work is anticipated needing street closures. The site will be closed on July 4th. Happy Independence Day!

June 19, 2018

Here’s what you can expect to see on site in the next two weeks:

This week, the construction crew will be pouring the 5th floor deck in the tower portion of the site and erecting formwork for the 6th floor deck.  We’ll continue with general housekeeping (cleanup and collection of trash and construction debris) and implementing site safety protocols.  There is no anticipated off-site utility work or street closures.

Next week (starting 6/25), the crew will be prepping for the cellar deck of Mat “C”, closest to One Pierrepont, for the concrete pour the week of 7/3.  On the tower portion, we’ll pour the 6th floor deck and erect formwork for the 6th floor columns and 7th floor deck.  We will continue with the general housekeeping mentioned above.  No off-site utility work or street closures will occur.

June 5, 2018

It’s been a couple of weeks since our last update.  Hope everyone enjoyed Memorial Day Weekend!  Things are moving along on site.  ConEd finished their street work and the final fencing is installed along Clinton Street.  We are completely done with the foundations portion of the project and are starting to bring the last floors of the basement up to grade.  We have poured up to the 2nd floor and expect to pour the 3rd floor this week.  Things are happening quickly!

280 CADMAN
PLAZA WEST
×